Back to: Britain’s grid bottlenecks drive a £47.9 million balancing bill
Understand this story · 2 of 3

Electricity transmission constraint

The limits preventing available northern generation from reaching demand farther south.

A limit on how much electricity can be carried safely through part of the transmission network under the conditions at the time.

Location matters as well as quantity

A transmission constraint limits the movement of electricity through a part of the network. The system needs not only enough generation overall but also a safe way to carry electricity to the places using it. A large amount of available power in one location cannot be treated as automatically available everywhere.

Operating within the network’s limits

Cables and associated equipment have safe operating limits. When expected flows would exceed those limits, the operator can reduce generation on one side of the constraint and increase supply elsewhere. Payments can therefore arise both for unused output and for replacement output. Building suitable network capacity can relieve a constraint, but operational measures are needed in the meantime.

A hypothetical pair of regions

Imagine a northern region has strong wind generation and a southern region has high demand. The connecting network cannot safely carry all the northern output. Reducing northern generation and buying southern generation can keep the system secure even though total generating equipment is sufficient. This illustrates why the location of power affects its usefulness.

Capacity and energy are different measures

Generation capacity measures the rate at which equipment can produce power. Energy measures production over time. A claim that some generating capacity was unavailable to the system does not establish the amount of energy lost over a day without knowing duration and operating conditions. Transmission investment and operational are also separate measures.