Jamaica targets December road access relief for Montego Bay–Negril corridor
Reported Nov 11, 2026Quickanomics write-up updated Nov 11, 2026, version 24 min read
Follow the developing storyMatthew Samuda rejected moving all western pipeline construction to night, citing a 50 per cent cost increase, and said 18 to 24 months of pipe-laying remained. Read the current version
Ministers and engineers set December 15 road-access targets and outlined diversions and selected night work after complaints about western Jamaica’s congestion.

The short version
The Government is targeting trafficable road sections by December 15 and better coordination of overlapping works. disputes the proposed alternatives, while says essential pipe replacement will continue into 2028.
Driveable sections before the winter season
Contractors are targeting December 15 to make critical parts of the Montego Bay–Negril road corridor trafficable, as ministers respond to complaints about journeys that are disrupting tourism and workers’ commutes. The Gleaner reported the commitments after Tuesday’s meeting of government, engineering and private-sector representatives in Montego Bay.
, minister of state in the Ministry of Industry, Investment and Commerce, said complaints from workers, visitors and businesses had reached the Government, including Prime Minister . Simultaneous road rehabilitation, water upgrades and post-hurricane reconstruction had created severe disruption across St James, Hanover and Westmoreland, he said.
linked time lost in traffic to and businesses’ ability to operate. He said the projects should proceed without major delays, but agencies needed better coordination, contractors should accelerate work and alternative routes had to be made passable.
of SJE Consultants, supervising engineer for Packages Three and Four of the SPARK programme, said about J$4.1 billion was being spent on seven sections between Howard Cooke Boulevard and Negril. The immediate objective is a driveable roller-compacted concrete surface, with the final asphalt layer to follow.
Westgreen Avenue, Great River and Lucea are the priorities. The target includes paving the disturbed Great River section, carrying four lanes on Westgreen between Barnett Street and Howard Cooke Boulevard, and making affected Lucea sections trafficable by mid-December. cautioned that alternative roads can need repairs or be too narrow for large vehicles, and said police assistance would help address bottlenecks and traffic discipline.
Alternatives and night work have limits
Hanover Eastern MP and opposition tourism spokesperson argued that the alternatives under consideration mainly help residents reaching communities, schools and health facilities. She questioned their practicality for visitors and tourism workers bound for Negril.
proposed urgent patching and bushing of Kingsvale–Glasgow road, connecting to Green Island. She estimated a journey of around 35 to 40 minutes through the affected area, compared with motorists waiting up to 90 minutes before reaching existing alternative routes. Those are her estimates, not a measured improvement already achieved.
Water Minister said major pipe-laying would be timed around school traffic and hotel . More difficult bridge crossings would be undertaken in quieter accommodation periods, and selected night operations were planned where disruption would be especially severe.
Night work carries a cost: put it about 50 per cent above daytime operations because of extra lighting and equipment. He said tourism stakeholders, including the Jamaica Hotel and Tourist Association, were being consulted about the least disruptive periods.
The US$170 million first phase of the western water programme involves replacing approximately 67 kilometres of major pipelines, with pipe-laying continuing into 2028, said. He rejected suspending the works, citing the risk of another intense drought next year and water losses above 70 per cent in some network sections. The December road target does not mean completion of that water programme.
New commitments follow hotelier warnings
The meeting follows earlier appeals over access to Negril. On November 8, the Sunday Gleaner reported ’s request for Holness to visit and meet stakeholders about simultaneous projects and pipe-laying on Norman Manley Boulevard. warned operators might eventually need to refund visitors’ deposits; the report did not establish refunds already being paid.
Hoteliers described separate rainy-weather journeys from Sangster of up to four hours and three hours. An unnamed JUTA driver described a five-hour Friday trip in the reverse direction, from Negril to Montego Bay. Those accounts describe particular trips rather than a measured corridor average.
Mozio’s commercial survey placed Negril 91st and Montego Bay seventh among 100 beach destinations for airport access, weighting driving time at 60 per cent and distance at 40 per cent. It assessed ground access, not the quality of accommodation or beaches. Long transfers can take a greater share of a short stay. Mozio chief executive advised comparing services, prices and estimated travel times against travellers’ needs and budgets.
The earlier report cited Jamaica Tourist Board totals of 2.34 million visitors and approximately US$2.5 billion in tourism earnings for January–August 2026. Those island-wide figures describe the industry’s scale; they do not quantify Negril’s traffic-related losses.
Understand this story
Connect travel delays with productive working time, then understand how hotel occupancy affects the scheduling of disruptive works.
Sources and reporting notes
- 1. Jamaica GleanerGovernment scrambles to ease Montego Bay–Negril road chaos ahead of winter season (opens in a new tab)
- 2. Jamaica GleanerGleaner: Negril’s road nightmare and tourism access (opens in a new tab)
What remains unclear
Will the critical road sections be trafficable by December 15?
Which alternative routes will be made suitable for Negril-bound tourism traffic?
Which sources support each point?
A Tuesday, November 10, 2026 meeting in Montego Bay brought ministers, engineers, the National Works Agency, National Water Commission and private-sector representatives together after complaints about congestion between Montego Bay and Negril. State minister Delano Seiveright said workers, tourists and businesses were losing time as roadworks, water upgrades and post-hurricane rebuilding overlapped across St James, Hanover and Westmoreland.
Seiveright said projects should continue, with better agency coordination, passable alternative routes and accelerated contractor work. He linked delays to lost productivity and said some complaints reached Prime Minister Andrew Holness.
Andrew Evans of SJE Consultants, supervising engineer for SPARK Packages Three and Four, said about J$4.1 billion was being spent on seven corridor sections from Howard Cooke Boulevard to Negril. Contractors aim to make critical sections trafficable by December 15, 2026, using roller-compacted concrete before the final asphalt layer.
The immediate road priorities are Westgreen Avenue, Great River and Lucea. The target includes paving the disturbed Great River section, four traffic lanes on Westgreen between Barnett Street and Howard Cooke Boulevard, and trafficable Lucea sections by mid-December. Some alternative roads need remedial work or are too narrow for large vehicles; Evans said police assistance is important for bottlenecks and traffic discipline.
Hanover Eastern MP and opposition tourism spokesperson Andrea Purkiss urged patching and bushing of Kingsvale–Glasgow road linking to Green Island. She said proposed alternatives chiefly serve local communities, schools and health facilities, rather than Negril-bound tourism traffic. She estimated her proposed route could take 35 to 40 minutes versus waits up to 90 minutes before reaching existing alternatives.
Water Minister Matthew Samuda said major pipe-laying would be scheduled around hotel occupancy and school traffic, with difficult bridge crossings in quieter hotel periods and selected night work where disruption is severe. He said night work costs about 50 per cent more because of lighting and equipment.
Samuda said the US$170 million first phase of the western water programme replaces about 67 kilometres of major pipelines, with pipe-laying continuing into 2028. He said suspension is not an option given the risk of another intense drought next year, and water losses exceed 70 per cent in some existing network sections.
The November 8 Gleaner report described hoteliers’ rainy-weather Sangster-to-Negril trips lasting up to four hours, other unnamed hoteliers’ reports of three hours, and an unnamed JUTA driver’s five-hour Friday journey in the reverse direction from Negril to Montego Bay. These are separate accounts, not a route average. Lee Issa asked Andrew Holness to visit and meet stakeholders over simultaneous road projects and Norman Manley Boulevard pipe-laying, warning that operators might eventually need to refund visitors’ deposits; refunds were not reported as already paid.
Mozio ranked Negril 91st and Montego Bay seventh among 100 beach destinations for airport accessibility, weighting driving time 60 per cent and distance 40 per cent. The commercial study concerns ground access rather than beach or hotel quality. Longer transfers can consume a larger part of short holidays.
Mozio chief executive Nicole Kerr advised comparing airport-to-destination services, prices and estimated travel times with a traveller’s needs and budget. Jamaica Tourist Board figures cited in the report showed 2.34 million island-wide visitors and about US$2.5 billion in tourism earnings in January–August 2026, not losses attributable to Negril traffic.