Samuda rules out blanket night pipeline work on Montego Bay–Negril corridor
Reported Nov 13, 2026Quickanomics write-up updated Nov 13, 2026, version 34 min read
Follow the developing storyMatthew Samuda rejected moving all western pipeline construction to night, citing a 50 per cent cost increase, and said 18 to 24 months of pipe-laying remained.

The short version
The water minister rejects blanket overnight pipeline construction on cost grounds, while promising selected night operations and regular coordination. The latest account puts remaining pipe-laying at 18 to 24 months, separate from December’s road-access targets.
sets out the cost and construction limits
Water, Environment and Climate Change Minister says shifting all western pipeline replacement work to night would raise construction costs by 50 per cent, an increase the Government cannot afford on the US$170 million first phase of the Western Resilience Water Project.
His explanation, reported by the Gleaner on November 13, came at a Montego Bay stakeholder meeting convened by , state minister in the Ministry of Industry, Investment and Commerce. Tourism, chamber and police representatives were involved in addressing disruption to businesses, commuters and visitors.
said particularly disruptive crossings and selected other locations would be worked on overnight. The distinction is between targeted night operations and moving the whole programme into the night.
The project was approximately six months into construction, with another 18 to 24 months of pipe-laying remaining, he said. Its first phase replaces 67 kilometres of transmission mains, including 36-inch ductile iron sections requiring specialised cranes and heavy equipment. He put a crew’s progress at six to eight large pipes a day, adding that deploying more crews simultaneously could worsen congestion.
Business groups support restraint and ask for better notices
Montego Bay Chamber of Commerce and Industry president backed the spending restraint. He said his experience with round-the-clock work showed that longer hours did not necessarily deliver benefits worth the added cost. Construction was different from hospitality’s established shifts, and overnight workers would demand additional pay, he argued.
Negril Chamber of Commerce president also recognised the financial constraints, including lighting and wage premiums, while supporting overnight work where daytime disruption would be particularly severe.
stressed regular communication about schedules, closures and alternative routes through the chambers, the Jamaica Hotel and Tourist Association, social media and traditional media. He welcomed senior officials’ and police representatives’ participation as a response to business concerns.
Road-access commitments precede the longer pipeline finish
The November 11 Gleaner report described ’s concern about tourists spending hours in transit, workers arriving late and businesses struggling to operate. Complaints had reached Prime Minister . Road rehabilitation, water upgrades and post-hurricane reconstruction overlapped across St James, Hanover and Westmoreland.
linked the lost time to and called for better coordination among agencies, faster contractor work and passable alternatives, without major delays to the projects. Ministers, engineers, the National Works Agency, National Water Commission and private-sector representatives had met in Montego Bay.
of SJE Consultants, supervising engineer for SPARK Packages Three and Four, said about J$4.1 billion was being spent on seven sections from Howard Cooke Boulevard to Negril. The target is trafficable critical sections by December 15, on roller-compacted concrete before the final asphalt layer.
The priorities include paving the disturbed Great River section, four lanes on Westgreen Avenue between Barnett Street and Howard Cooke Boulevard, and trafficable Lucea sections by mid-December. said alternatives could require repairs or be too narrow for large vehicles, making police assistance important for bottlenecks and traffic discipline.
Hanover Eastern MP and opposition tourism spokesperson disputed the proposed alternatives’ usefulness for Negril-bound tourism traffic, saying they mainly served communities, schools and health facilities. She urged patching and bushing of Kingsvale–Glasgow road, connecting to Green Island. Her estimate of 35 to 40 minutes through the area compared with waits of up to 90 minutes before existing alternatives was a proposal, not an achieved reduction.
said school traffic and hotel would inform pipe-laying schedules, with difficult bridge crossings in quieter hotel periods after consultation including the Jamaica Hotel and Tourist Association. He said pipe-laying would continue into 2028. He rejected suspension because of possible intense drought in 2027 and water losses exceeding 70 per cent in some existing sections. December’s road target is therefore separate from finishing the water programme.
Hotelier concerns and airport-access comparisons
On November 8, asked Holness to visit Negril and meet stakeholders over simultaneous projects and Norman Manley Boulevard pipe-laying. He warned operators might need to refund visitor deposits; refunds were not reported as already paid.
Hoteliers described separate rainy-weather transfers from Sangster of up to four hours and three hours. An unnamed JUTA driver recounted a five-hour Friday journey from Negril to Montego Bay. The accounts cover different trips and directions, rather than a corridor average.
Mozio’s commercial study placed Negril 91st and Montego Bay seventh among 100 beach destinations for airport access, weighting driving time at 60 per cent and distance at 40 per cent. It assessed ground access, not beach or hotel quality. Long transfers consume a larger share of a short stay. Mozio chief executive advised comparing services, prices and estimated times with travellers’ needs and budgets.
The earlier report cited Jamaica Tourist Board figures of 2.34 million visitors and about US$2.5 billion in tourism earnings in January–August 2026. Those island-wide totals describe the industry’s scale, not Negril’s traffic-related losses.
Understand this story
Connect delays with productive working time, then understand why hotel occupancy affects the scheduling of disruptive works.
Sources and reporting notes
- 1. Jamaica GleanerSamuda rules out night work on pipeline project out west (opens in a new tab)
- 2. Jamaica GleanerGovernment scrambles to ease Montego Bay–Negril road chaos ahead of winter season (opens in a new tab)
- 3. Jamaica GleanerGleaner: Negril’s road nightmare and tourism access (opens in a new tab)
What remains unclear
Will the critical road sections be trafficable by December 15?
Which alternative routes will be made suitable for Negril-bound tourism traffic?
Which sources support each point?
Water, Environment and Climate Change Minister Matthew Samuda said doing all pipeline replacement work at night would cost 50 per cent more. He said the Government could not add that amount to the US$170 million first phase of the Western Resilience Water Project.
Samuda said selected crossings and other locations expected to cause especially severe disruption would be worked on at night. His comments came at a Montego Bay stakeholder meeting convened by industry ministry state minister Delano Seiveright, with tourism, chamber and police representatives involved.
Montego Bay Chamber of Commerce and Industry president Jason Russell supported the spending restraint. He said experience with round-the-clock work showed that more hours did not necessarily justify the added cost, construction differed from established hotel shift work and overnight workers would require extra pay.
Negril Chamber of Commerce president Damian Salmon acknowledged the financial constraints and costs of lighting and wage premiums, while supporting night work where daytime disruption would be particularly serious.
Salmon called for regular work-schedule, closure and alternative-route updates through chambers, the Jamaica Hotel and Tourist Association, social media and traditional media. He welcomed senior officials’ and police representatives’ participation.
Samuda said the project was approximately six months into construction, with 18 to 24 months of pipe-laying still remaining.
The first phase replaces 67 kilometres of transmission pipelines, including 36-inch ductile iron mains requiring specialised cranes and heavy equipment. Samuda said a crew could install six to eight large pipes per day and that adding simultaneous crews could worsen congestion.
The November 11 report described complaints from tourists, workers and businesses about overlapping road rehabilitation, water upgrades and post-hurricane reconstruction across St James, Hanover and Westmoreland. Delano Seiveright said some complaints reached Prime Minister Andrew Holness, and linked traffic delays to lost productivity and difficulty running businesses.
Seiveright said projects should continue without major delays, with better agency coordination, passable alternatives and faster contractor work. Ministers, engineers, the National Works Agency, National Water Commission and private-sector representatives met in Montego Bay.
Andrew Evans of SJE Consultants, supervising engineer for SPARK Packages Three and Four, said approximately J$4.1 billion was being spent on seven corridor sections from Howard Cooke Boulevard in Montego Bay to Negril. The target was to make critical sections trafficable by December 15, with roller-compacted concrete before the final asphalt surface.
Road priorities were Westgreen Avenue, Great River and Lucea: paving the disturbed Great River section, four lanes on Westgreen between Barnett Street and Howard Cooke Boulevard, and trafficable Lucea sections by mid-December. Evans said some alternative roads needed repairs or were too narrow for large vehicles and police help was important for bottlenecks and traffic discipline.
Hanover Eastern MP and opposition tourism spokesperson Andrea Purkiss said proposed alternatives mainly served communities, schools and health facilities rather than Negril-bound tourism traffic. She urged patching and bushing of Kingsvale–Glasgow road connecting to Green Island, estimating 35 to 40 minutes through the area against waits of up to 90 minutes before reaching existing alternatives.
Samuda said major pipe-laying would account for school traffic and hotel occupancy, after consultation including the Jamaica Hotel and Tourist Association. Difficult bridge crossings would be scheduled for lower hotel occupancy, with selected night work where disruption was severe. He put night work about 50 per cent above daytime costs because of lighting and equipment.
Samuda said the US$170 million first phase would replace about 67 kilometres of major pipelines, with pipe-laying continuing into 2028. He rejected suspension because of another possible intense drought in 2027 and water losses above 70 per cent in some existing network sections.
The November 8 report said Lee Issa asked Andrew Holness to visit Negril and meet stakeholders about simultaneous road projects and pipe-laying on Norman Manley Boulevard. Issa warned operators might have to refund visitor deposits, rather than saying refunds had already been paid.
Hoteliers gave separate rainy-weather Sangster-to-Negril transfer accounts of up to four hours and three hours. An unnamed JUTA driver described a five-hour Friday journey from Negril to Montego Bay. These were individual accounts, not a corridor average.
Mozio’s commercial study ranked Negril 91st and Montego Bay seventh among 100 beach destinations for airport access, weighting driving time at 60 per cent and distance at 40 per cent. It measured ground access, not beach or hotel quality. Long transfers take a larger share of short holidays.
Mozio chief executive Nicole Kerr advised comparing transport services, prices and estimated times with visitors’ needs and budgets. Jamaica Tourist Board figures cited in the report showed 2.34 million island-wide visitors and about US$2.5 billion in tourism earnings in January–August 2026, not a calculation of Negril traffic losses.