JPS points to more hydropower after reported US$70 million fuel savings
Reported Oct 26, 2026Quickanomics write-up updated Oct 26, 2026, version 13 min read
Follow the developing story
The short version
JPS points to Jamaica’s potential after reporting fuel savings from its existing plants, but further capacity still requires water studies, environmental work, capital and time.
JPS points to a further hydro resource
Jamaica Public Service is highlighting the potential to develop more river-powered electricity, citing fuel savings and steady output from its existing hydro plants while acknowledging that new projects require substantial capital and long development periods.
The Gleaner reports that JPS operates nine generating units at six locations, with combined installed capacity of approximately 30 . uses flowing water to drive turbines and generators. measure the rate of power a plant can supply, while -hours measure electricity generated over a period.
, JPS vice-president of generation, says studies have identified potential for at least another 60 . He presents that as an untapped resource, rather than capacity already approved, financed or commissioned.
The existing sites are Upper White River, Lower White River and Roaring River in St Ann; Constant Spring in St Andrew; Rio Bueno in Trelawny, with two units; and Maggotty in St Elizabeth, with three. JPS, incorporated in 1923, now serves more than 700,000 customers. says one of its oldest hydro stations has operated for about eight decades and remains productive.
Savings and utilisation across 2022–2025
The report estimates that electricity generated by JPS hydro plants between 2022 and 2025 displaced the equivalent of more than 900,000 barrels of oil, avoiding more than US$70 million in fuel costs for customers. The amounts are cumulative estimates for that period, rather than annual savings or cash payments.
Over the same period, JPS hydro’s average was approximately 47%, compared with 29% for wind farms and 24% for solar facilities in the reported comparison. measures actual generation against the electricity that could be produced by running at full power throughout the period. It is different from the efficiency with which equipment converts energy.
When sufficient water is available, hydro can generate through the day and night without depending directly on sunlight or prevailing wind. Former JPS director says the plants’ long lives also support affordability and places existing JPS hydro facilities among the electricity system’s lowest-cost generation resources.
Storm preparation and the financing challenge
, JPS director of , says the hydro facilities sustained relatively minor damage during a Category 5 hurricane, with several returning quickly and helping restore electricity to affected communities. He says crews prepared for flooding by removing flood boards and emptying pipelines. Baker did not identify or date the hurricane in that account.
Jamaica’s policy target is for 50% by 2030. JPS contributes through its own renewable plants and by integrating electricity from independent wind and solar producers into the national network.
says further hydro development requires significant upfront funding, detailed studies of water flows and environmental effects, long development timelines and long periods to recover costs. He sees partnerships as a way to combine capital and technical expertise with long-term energy planning.
The wider transition involves several technologies. The report places hydro alongside solar, wind, and smarter electricity networks, with different resources contributing to the system rather than one technology meeting every need.
Understand this story
Distinguish generating capacity, electricity produced and the utilisation of a power plant.
- Hydropower
Electricity generated by using the energy of moving water to drive a turbine and generator.
- Electricity power and energy
Megawatts describe power at a moment; megawatt-hours describe electricity generated over time. The 30 MW existing fleet and additional 60 MW potential are capacity figures.
- Capacity factor
Actual electricity generation over a period divided by the amount possible from continuous operation at full power during that same period.
Sources and reporting notes
- 1. Jamaica GleanerJPS harnesses power of water and considers hydroelectricity’s potential (opens in a new tab)
What remains unclear
Which additional hydro sites would proceed and how their studies, construction and financing would be arranged.
Which sources support each point?
JPS operates nine hydroelectric generating units at six Jamaican locations, with approximately 30 MW of installed capacity. They are Upper White River, Lower White River and Roaring River in St Ann, Constant Spring in St Andrew, two units at Rio Bueno in Trelawny and three at Maggotty in St Elizabeth.
JPS, incorporated in 1923, serves more than 700,000 customers. Vice-president of generation Sameer Simms said one of its oldest hydro stations had operated for about eight decades and remained productive.
The Gleaner reported estimates that JPS hydro generation during 2022–2025 displaced the equivalent of more than 900,000 barrels of oil and avoided more than US$70 million in fuel costs for customers. These are estimated cumulative avoided fuel costs across that period, not annual cash payments.
Simms said studies identified potential for at least another 60 MW of hydropower, beyond approximately 30 MW being harnessed. The figure describes potential, not installed capacity or an approved, financed construction commitment.
Jamaica has a policy target of 50% renewable energy by 2030. JPS supports that aim through its own renewable generation and the integration of independent wind and solar producers into the national electricity network.
Peter Baker, identified in the October 26 Gleaner report as JPS director of renewables, said its hydro plants suffered relatively minor damage during a Category 5 hurricane, several returned quickly and helped restore service. He said flood boards had been removed and pipelines emptied before heavy flooding. The report does not identify or date the hurricane in this passage.
The 2022–2025 comparison reported by The Gleaner puts JPS hydro’s average capacity factor at about 47%, against 29% for wind farms and 24% for solar facilities. Hydro can run day and night when sufficient water is available, rather than depending directly on daylight or current wind.
Former JPS renewables director Newton Young said hydro’s steady contribution and long operating life helped affordability and described existing JPS hydro stations as among the system’s lowest-cost generation resources. These are his assessments.
Simms said new hydro development required substantial upfront funding, studies of water flows and environmental effects, long development times and long periods to recover costs. He said partnerships could combine capital and technical expertise with energy planning.
The Gleaner describes hydro as part of a wider Jamaican energy mix that also includes expanding solar, wind, battery storage and smarter electricity networks; it does not say hydro alone can deliver the energy transition.